HLI Ecohub Nam Ha Factory Project Progress Update – July 10, 2025

The HLI EcoHub Nam Ha construction site is entering an accelerated completion phase, with many key components being implemented simultaneously to ensure on-schedule handover.

FACTORY AREA – FINAL ITEMS BEING URGENTLY COMPLETED:

  • Restroom tiling is being fast-tracked to ensure integrated interior finishing.
  • Floor grinding is being completed to ensure flatness, load-bearing capacity, and aesthetics.
  • Emergency exit doors are being installed, ensuring safety and fire prevention standards are met.
  • Roof vent installation and canopy frame alignment are being carried out in parallel with the overall progress.

AUXILIARY AREAS – SYNCHRONIZED SUPPORT INFRASTRUCTURE DEPLOYMENT:

  • Underground Firefighting Water Tank: Internal waterproofing plastering has been completed, ensuring water storage capacity and fire safety.
  • Pump House, Waste House, Operations House: Roof waterproofing construction continues, enhancing the durability of auxiliary structures.
  • Kiosk Substation: Beam and perimeter formwork has been removed, preparing for the next finishing phase.

Video HLI EcoHub Nam Ha Factory Project Progress Update:

HLI ECOHUB NAM HA READY-BUILT FACTORY
– Location: Nam Ha Hamlet, Tra Tan Commune, Lam Dong Province
– Hotline: 0964 582 346
– Email: contact@hoalonginvest.com
– Office: 19 Tran Quy Kien Street, Binh Trung Ward, HCM City

预约参观厂房

请填写以下完整信息。我们将尽快与您联系。

FACTORY TOUR REGISTRATION

Please leave your information, and we will contact you for a consultation as soon as possible.