HLI EcoHub Nam Ha is now entering an accelerated phase, with a series of key components being implemented simultaneously:
FACTORY AREA
- Fiber-reinforced concrete pouring for the factory floor is underway.
- Wall sheeting installation and construction of the ground floor and mezzanine walls are in progress.
- Internal roads are being built to ensure flexible infrastructure connectivity.
AUXILIARY AREAS & MEP
- Fire Protection System (FPS) and restroom construction are being carried out.
- Grounding system installation is underway, ensuring electrical safety for the entire project.
- Pump house, waste disposal facility, and operations building construction are nearing completion.
- Installation of power supply conduits for exit lights and EMC is in progress, preparing for lighting and operational systems.
Actual images from the construction site are continuously being updated! HLI EcoHub Nam Ha is steadily taking shape, promising a modern and sustainable production space.
Contact us today to schedule a site visit!

HLI ECOHUB NAM HA READY-BUILT FACTORY
– Location: Nam Ha Hamlet, Tra Tan Commune, Lam Dong Province
– Hotline: 0964 582 346
– Email: contact@hoalonginvest.com
– Office: 19 Tran Quy Kien Street, Binh Trung Ward, HCM City